active: false
|
||||
tags:
|
||||
- project
|
||||
- eg
|
||||
created: 2024-11-01
|
||||
---
|
||||
## Goal
|
||||
|
||||
Rewire Poulsbo location with:
|
||||
|
||||
- Lighting zones
|
||||
- Wall and ceiling outlets
|
||||
- One breaker for each room
|
||||
- Conduit for future kitchen
|
||||
- Control boxes for all rooms
|
||||
|
||||
Set up escape room network hardware & software.
|
||||
|
||||
- 8 ethernet cables for cameras (8W each = 64W)
|
||||
- 3 for WiFi AP's (21W each = 63W)
|
||||
- 5 ethernet cables for room controllers
|
||||
- 5 ethernet cables for GM stations
|
||||
- 1 ethernet for cable modem
|
||||
## To Do
|
||||
|
||||
- [x] Take USB switcher, HDMI cable, keyboard and mouse to the EG and hook up laptop ➕ 2025-04-06 ✅ 2025-04-06
|
||||
- [x] Install and configure new modem ➕ 2024-07-13 ✅ 2025-04-25
|
||||
- [x] Put track down wall for network and coax cable ➕ 2024-12-09 ✅ 2025-03-21
|
||||
- [x] Wire up AP's ➕ 2024-07-13 ✅ 2025-03-27
|
||||
- [x] Install WiFi AP's ➕ 2024-07-13 ✅ 2025-03-27
|
||||
- [x] Install and configure UniFi Gateway ➕ 2024-07-13 ✅ 2025-03-27
|
||||
- [x] Install the UPS ➕ 2025-03-02 ✅ 2025-03-27
|
||||
- [x] Run ethernet cable for cameras ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Run ethernet cable to each of the control boxes ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Run ethernet cable to each of the WiFi AP's ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Cut out pieces for remaining 4 boxes ➕ 2025-03-02 ✅ 2025-03-04
|
||||
- [x] Pre-drill screw holes for screws in 4 boxes ➕ 2025-03-02 ✅ 2025-03-04
|
||||
- [x] Build server rack ➕ 2024-09-23 ✅ 2025-03-16
|
||||
- [x] Drill green light to remaining 4 boxes ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Cut conduit, vent and fan holes in remaining 4 boxes ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Attach plugs and 3/8" flex conduit to 4 boxes ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Attach vents to 4 boxes ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Attach fans to 4 boxes ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Remove wall for in room #1 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Install box #1 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Install box #1 plug & switch boxes ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Wire box #1 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Replace wall in room #1 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Install box #3 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Install box #3 plug & switch boxes ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Wire box #3 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Install box #4 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Install box #4 plug & switch boxes ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Wire box #4 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Remove wall in room #5 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Install box #5 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Install box #5 plug & switch boxes ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Wire box #5 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Replace wall in room #5 ➕ 2025-03-02 ✅ 2025-03-16
|
||||
- [x] Install wire racks in ceiling of Odin's Dilemma ➕ 2025-02-11 ✅ 2025-03-02
|
||||
- [x] Configure RingCentral ➕ 2025-02-13 ✅ 2025-02-13
|
||||
- [x] Order cable modem ⏫ ➕ 2024-11-03 ✅ 2024-12-01
|
||||
- [x] Order WiFi AP's ⏫ ➕ 2024-07-13 ✅ 2024-12-01
|
||||
- [x] Order router micro PC machine ⏫ ➕ 2024-07-13 ✅ 2024-12-01
|
||||
- [x] Order a battery backup device ⏫ ➕ 2024-07-13 ✅ 2024-12-01
|
||||
- [x] Order a network hub ➕ 2024-12-01 ✅ 2025-02-11
|
||||
- [x] Install plug in control box ➕ 2025-02-23 ✅ 2025-03-02
|
||||
- [x] Install green light in control box ➕ 2025-02-28 ✅ 2025-03-02
|
||||
- [x] Install power switch ➕ 2025-02-28 ✅ 2025-03-02
|
||||
- [x] Install light switch ➕ 2025-02-28 ✅ 2025-03-02
|
||||
- [x] Attach control box to the wall ➕ 2025-02-23 ✅ 2025-03-02
|
||||
- [x] Mark exit signs with broken lights ➕ 2025-02-11 ✅ 2025-02-16
|
||||
- [x] Put all exit signs back up ➕ 2025-02-11 ✅ 2025-02-16
|
||||
- [x] Install switch to both ends of the control room ➕ 2025-01-14 ✅ 2025-01-31
|
||||
- [x] Install switch at the end of room 5 for meeting room lights ➕ 2025-01-14 ✅ 2025-01-31
|
||||
- [x] Install plug on room 5 outer wall ✅ 2025-01-31
|
||||
- [x] Install room 1 exit signs ➕ 2024-12-11 ✅ 2025-01-31
|
||||
- [x] Install room 2 exit signs ➕ 2024-12-11 ✅ 2025-02-11
|
||||
- [x] Install room 3 exit signs ➕ 2024-12-11 ✅ 2025-02-11
|
||||
- [x] Install room 4 exit signs ➕ 2024-12-11 ✅ 2025-02-11
|
||||
- [x] Install room 5 exit signs ➕ 2024-12-11 ✅ 2025-02-11
|
||||
- [x] Install front door exit sign ➕ 2025-01-14 ✅ 2025-01-31
|
||||
- [x] Install back door exit sign ➕ 2025-01-14 ✅ 2025-01-31
|
||||
- [x] Install back hallway exit sign ➕ 2025-01-14 ✅ 2025-01-31
|
||||
- [x] Install middle hallway exit sign ➕ 2025-01-14 ✅ 2025-01-31
|
||||
- [x] Install front hallway exit sign ➕ 2025-01-14 ✅ 2025-01-31
|
||||
- [x] Install control room front exit sign ➕ 2025-01-14 ✅ 2025-01-31
|
||||
- [x] Install control room back exit sign ➕ 2025-01-14 ✅ 2025-01-31
|
||||
- [x] Electrical inspection ➕ 2025-01-17 ✅ 2025-01-31
|
||||
- [x] Install kitchen conduit ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 1 conduit ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 1 wiring ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 1 lights ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 2 conduit ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 2 wiring ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 2 lights ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 3 conduit ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 3 wiring ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 3 lights ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 4 conduit ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 4 wiring ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 4 lights ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 5 conduit ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 5 wiring ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Install room 5 lights ➕ 2024-12-11 ✅ 2025-01-14
|
||||
- [x] Bend the back light conduit to go over back lights/power conduit ➕ 2024-12-16 ✅ 2024-12-29
|
||||
- [x] Install back hall/power wiring ➕ 2024-12-11 ✅ 2024-12-29
|
||||
- [x] Install back hall lights ➕ 2024-12-20 ✅ 2024-12-29
|
||||
- [x] Install toilet conduit ➕ 2024-12-20 ✅ 2024-12-29
|
||||
- [x] Install toilet light/switch/fan/plug ➕ 2024-12-20 ✅ 2024-12-29
|
||||
- [x] Install utility room conduit ➕ 2024-12-20 ✅ 2024-12-29
|
||||
- [x] Install utility light/switch ➕ 2024-12-20 ✅ 2024-12-29
|
||||
- [x] Install meeting conduit ➕ 2024-12-11 ✅ 2024-12-29
|
||||
- [x] Install meeting wiring ➕ 2024-12-11 ✅ 2024-12-29
|
||||
- [x] Install meeting lights ➕ 2024-12-20 ✅ 2024-12-29
|
||||
- [x] Install escape room conduit to breaker ➕ 2024-12-11 ✅ 2024-12-29
|
||||
- [x] Install kitchen conduit to breaker ➕ 2024-12-11 ✅ 2024-12-29
|
||||
- [x] Install kitchen conduit ➕ 2024-12-11 ✅ 2024-12-29
|
||||
- [x] Install control room lights ✅ 2024-12-14
|
||||
- [x] Install front/front hallway/middle hallway lights ➕ 2024-12-11 ✅ 2024-12-14
|
||||
- [x] Install back conduit to breaker ➕ 2024-12-11 ✅ 2024-12-14
|
||||
- [x] Add back lighting/meeting area lighting circuit artboard ➕ 2024-12-09 ✅ 2024-12-20
|
||||
- [x] Add back power circuit artboard ➕ 2024-12-09 ✅ 2024-12-20
|
||||
- [x] Add meeting area power artboard ➕ 2024-12-09 ✅ 2024-12-20
|
||||
- [x] Buy more collars, black/white 12 AWG wire, pack of screw drivers, deWalt driver bits ➕ 2024-12-14 ✅ 2024-12-20
|
||||
- [x] Return 4" boxes and covers to Silverdale ➕ 2024-11-23 ✅ 2024-12-20
|
||||
- [x] Install back hall lighting/power conduit ➕ 2024-12-11 ✅ 2024-12-20
|
||||
- [x] Move the heating circuit up and above the rafters ➕ 2024-11-26 ✅ 2024-12-09
|
||||
- [x] Get a big printout of the wiring diagram ➕ 2024-11-26 ✅ 2024-12-09
|
||||
- [x] Move the outside light circuit up above the rafters ➕ 2024-11-26 ✅ 2024-12-09
|
||||
- [x] Remove the conduit around the lighting circuits ➕ 2024-11-26 ✅ 2024-12-09
|
||||
- [x] More 4" boxes with earth connectors ➕ 2024-12-02 ✅ 2024-12-09
|
||||
- [x] Flat nailing plates ➕ 2024-11-23 ✅ 2024-12-02
|
||||
- [x] Get a large printout of the electrical plan ➕ 2024-11-22 📅 2024-11-25 ✅ 2024-12-02
|
||||
- [x] 22 4" boxes with earth nub ➕ 2024-11-23 ✅ 2024-12-02
|
||||
- [x] Tool belt for Carmen ➕ 2024-11-23 ✅ 2024-12-02
|
||||
- [x] Count how many big light fixtures are in the space now ➕ 2024-11-01 ✅ 2024-11-02
|
||||
- [x] How far apart or the roof joists and how many? ➕ 2024-11-01 ✅ 2024-11-02
|
||||
- [x] What is power draw of the light fixtures? ➕ 2024-11-01 ✅ 2024-11-02
|
||||
- [x] How many big lights on each circuit right now? ➕ 2024-11-01 ✅ 2024-11-02
|
||||
- [x] What is the power draw of the small can light fixtures? ➕ 2024-11-01 ✅ 2024-11-02
|
||||
- [x] Order cameras 🔺 ➕ 2024-09-23 ✅ 2024-10-30
|
||||
- [x] Watch videos on how to bend EMT conduit 🔺 ➕ 2024-11-06 ✅ 2024-11-22
|
||||
- [x] Apply for the L&I permit for the space and display 🔺 ➕ 2024-11-06 ✅ 2024-11-22
|
||||
- [x] Remove the light switch circuit from beside he breaker box. ✅ 2024-11-22
|
||||
- [x] Open breaker box and remove all the stuff on the left side of the box ✅ 2024-11-23
|
||||
- [x] Add water heater to drawing ➕ 2024-11-01 ✅ 2024-11-22
|
||||
- [x] Add all control room outlets to the drawing ➕ 2024-11-01 ✅ 2024-11-22
|
||||
- [x] Add all lighting conduit and junction box runs to the drawing ➕ 2024-11-01 ✅ 2024-11-22
|
||||
- [x] Add circuits for each puzzle room to the drawing ➕ 2024-11-01 ✅ 2024-11-22
|
||||
- [x] Add meeting area, reception and back hall outlets to the drawing ➕ 2024-11-01 ✅ 2024-11-22
|
||||
- [x] Add location of cameras to the drawing ➕ 2024-11-01 ✅ 2024-11-22
|
||||
- [-] Add location of existing conduit runs to the drawing ➕ 2024-11-01 ❌ 2024-11-22
|
||||
- [x] Add location of the exit signs to the drawing ➕ 2024-11-01 ✅ 2024-11-22
|
||||
- [x] Order concrete screws ➕ 2024-11-03 ✅ 2024-11-22
|
||||
## Notes
|
||||
|
||||
Always power to switch first.
|
||||
Every switch & plug must have a neutral wire in the box.
|
||||
OK to use conduit as ground.
|
||||
Lights and plugs on separate circuits
|
||||
Every power line from a breaker must have a matching neutral line.
|
||||
Exit signs must be fed by the lighting circuits, ahead of any switching.
|
||||
|
||||
30 joists, 32" on center.
|
||||
|
||||
Power draw of lights is between 50W and 65W each.
|
||||
|
||||
There are 54 big light fixtures and 8 small light fixtures. There are currently 46 big light fixtures currently. Kitchen will require at least 6 circuits all 20A with 12/2 NM and GFCI/AFCI:
|
||||
|
||||
- Fridge
|
||||
- Dishwasher
|
||||
- Garbage Disposal
|
||||
- Microwave Oven
|
||||
- Small Appliance #1
|
||||
- Small Appliance #2
|
||||
|
||||
A cook top requires:
|
||||
|
||||
- 220V/50A 6/3 NM cable
|
||||
|
||||
Separate circuit for the alarm and camera system.
|
||||
|
||||
16 exit sign lights.
|
||||
|
||||
![[Breaker Labels.pdf]]
|
||||
## References
|
||||
|
||||
- [Multiwire Branch Circuit - Electrical 101](https://www.electrical101.com/multiwire-branch-circuit.html)
|
||||
- [National Electrical Code - Multiwire Branch Circuit - Transworld Electric](https://twielectric.com/national-electrical-code-multiwire-branch-circuit)
|
||||
- https://learnmetrics.com/how-many-outlets-on-a-15-amp-20-amp-30-amp-circuit-nec/
|
||||
- https://www.indeed.com/career-advice/finding-a-job/religious-degree-jobs
|
||||
- https://www.amazon.com/Sunco-Selectable-Temperature-Dimmable-Dustproof/dp/B0BWLH379Z
|
||||
- [How Many Outlets On A 15 Amp, 20 Amp, 30 Amp Circuit? (NEC 210.21)](https://learnmetrics.com/how-many-outlets-on-a-15-amp-20-amp-30-amp-circuit-nec)
|
||||
- [Electrical Circuit Requirements for Kitchens](https://www.thespruce.com/kitchen-wiring-circuits-1152911)
|
||||
- https://www.bradyid.com/resources/wiring-color-codes
|
||||
- https://lni.wa.gov/licensing-permits/electrical/electrical-permits-fees-and-inspections/purchase-permits-request-inspections
|
||||
- https://www.lni.wa.gov/forms-publications/F500-109-000.pdf
|
||||
- https://www.wikihow.com/Install-Electrical-Conduits
|
||||
- https://www.nema.org/docs/default-source/technical-document-library/steel-conduit-and-emt-proven-to-meet-the-nec-reg.pdf
|
||||
- https://diy.stackexchange.com/questions/74977/is-an-explicit-ground-wire-required-through-steel-conduit
|
||||
- https://www.homedepot.com/p/Southwire-500-ft-14-Gauge-White-Solid-CU-THHN-Wire-11580858/203401597
|
||||
### NFPA 70 NEC 2023 Extracts
|
||||
|
||||
#### Connectors
|
||||
|
||||
250.8 Connection of Grounding and Bonding Equipment.
|
||||
(A) Permitted Methods. Equipment grounding conductors,
|
||||
grounding electrode conductors, and bonding jumpers shall be
|
||||
connected by one or more of the following means:
|
||||
(1) Listed pressure connectors
|
||||
(2) Terminal bars
|
||||
(3) Pressure connectors listed ao; grounding and bonding
|
||||
equipment
|
||||
(4) Exothermic welding processes;
|
||||
(5) Machine screw-type fasteners that engage not Jcs. o; than
|
||||
two thrcado; or arc secured "ith a nut
|
||||
(6) Thread-forming machine screws dtal engage not lcs. o; than
|
||||
two threads; in dlc enclosure
|
||||
(7) Connections that arc part of a listed a"l.o;cmbly
|
||||
(8) Othcr listed means
|
||||
(B) Methods Not Permitted. Connection devices or fittings
|
||||
that depend solely on solder shall not be used.
|
||||
|
||||
### Control Boxes
|
||||
|
||||
- https://www.amazon.com/Nilight-90014E-Rocker-Toggle-Warranty/dp/B07QKFD7Z7
|
||||
- https://www.amazon.com/DaierTek-125VAC-Waterproof-Automotive-Aircraft/dp/B07T6YNRZS
|
||||
|
||||
### WiFi
|
||||
|
||||
- Escape Gallery WiFi password - `Berserker!`
|
||||
- [Packet Sender - Free utility to for sending / receiving of network packets. TCP, UDP, SSL.](https://packetsender.com/)
|
||||
- [ARRIS Surfboard S33 DOCSIS 3.1 Multi-Gigabit Cable Modem](https://www.amazon.com/gp/product/B08FMSC5WZ)
|
||||
- [Manage your APC battery backup system with this Linux command](https://opensource.com/article/21/12/linux-apcupsd)
|
||||
44
Projects/IT/Time Clock.md
Normal file
44
Projects/IT/Time Clock.md
Normal file
@@ -0,0 +1,44 @@
|
||||
---
|
||||
active: true
|
||||
tags: project
|
||||
created: 2026-06-08 19:27
|
||||
---
|
||||
## Goal
|
||||
|
||||
Build a time clock with:
|
||||
|
||||
- Hangs on the wall
|
||||
- LCD backlit clock
|
||||
- Fingerprint reader
|
||||
- Keypad for PIN and UI
|
||||
- Simple clock-in/clock-out interface
|
||||
- Way to generate a help request
|
||||
- System connects to a backend database that stores the timecard data
|
||||
- PoE for power
|
||||
- Built in speaker for sound effects
|
||||
## Tasks
|
||||
|
||||
- [x] Order parts ➕ 2026-06-08 ✅ 2026-07-11
|
||||
- [x] Print two halves of the case (rev 1) ➕ 2026-07-09 ✅ 2026-07-09
|
||||
- [x] Adjust case halves ➕ 2026-07-09 ✅ 2026-07-09
|
||||
- [x] Print rev 2 of cases ➕ 2026-07-09 ✅ 2026-07-09
|
||||
- [x] Install inserts into the case halves ➕ 2026-07-09 ✅ 2026-07-10
|
||||
|
||||
## Notes
|
||||
|
||||
The FPM10A (or DY50) is a highly popular optical fingerprint sensor that communicates over a TTL serial interface. It features an internal DSP chip that handles rendering, calculation, and feature-finding, making it exceptionally easy to use with an Arduino for smart locks and access control projects.
|
||||
### Wiring Connections
|
||||
|
||||
The FPM10A usually comes with a 6-pin connector, but you only need to use the 4 pins designated for power and serial communication.
|
||||
|
||||
- **Red Wire (VCC)**: Connect to Arduino **5V**
|
||||
- **Black/Green Wire (GND)**: Connect to Arduino **GND**
|
||||
- **Green Wire (TXD)**: Connect to Arduino Digital Pin **2**
|
||||
- **White/Yellow Wire (RXD)**: Connect to Arduino Digital Pin **3**
|
||||
## References
|
||||
|
||||
- [FPM10A Fingerprint Sensor](https://doc.grablo.co/en/docs/user-manuals/i-o-device/as608-fpm10a-fingerprint-sensor/#3.)
|
||||
- [`rppal uart`](https://docs.rs/rppal/latest/rppal/uart/index.html)
|
||||
- [`Grow-r502-a_fingerprint_sensor`](https://crates.io/crates/Grow-r502-a_fingerprint_sensor)
|
||||
- [`bell ding 1.wav`](freesound.org/people/5ro4/sounds/611113/)
|
||||
|
||||
Reference in New Issue
Block a user